规划设计对齐验证报告Checkpoint-21 / 联调前收口与决议口径同步)

  • 日期2026-03-30
  • 触发条件:完成 staging 预检增强、决议文档口径同步、TOK-007 证据链复跑

1. 结论

结论:本阶段对齐通过。已将“开发阶段能力收敛”与“真实 staging 待验”明确分离,避免对 M-021 与 token 风险做错误外推。

2. 对齐范围

  1. scripts/supply-gate/staging_precheck_and_run.sh
  2. reports/gates/staging_token_go_evidence_template_v1_2026-03-30.md
  3. docs/supply_gate_command_playbook_v1_2026-03-25.md
  4. review/final_decision_2026-03-31.md
  5. reports/supply_gate_review_2026-03-31.md
  6. reports/token_runtime_implementation_gap_review_2026-03-30.md
  7. reports/gates/token_runtime_readiness_2026-03-30_181926.md
  8. reports/gates/superpowers_stage_validation_2026-03-30_181925.md
  9. reports/gates/superpowers_release_pipeline_2026-03-30_181925.md
  10. review/outputs/tok007_release_recheck_2026-03-30_182149.md
  11. reports/gates/final_decision_consistency_2026-03-30_182149.md
  12. review/outputs/final_decision_candidate_from_tok007_2026-03-30_182149.md

3. 核查结果

核查项 结果 证据
staging 预检已纳入 M-021 前置检查 PASS staging_precheck_and_run.sh
联调证据回填模板可直接执行 PASS staging_token_go_evidence_template_v1_2026-03-30.md
Final Decision 中 M-021 口径与当前实现一致 PASS review/final_decision_2026-03-31.md
SUP 汇总风险描述与 TOK 差距复审一致 PASS reports/supply_gate_review_2026-03-31.md + reports/token_runtime_implementation_gap_review_2026-03-30.md
TOK-007 复审已显式纳入 M-021 输入 PASS tok007_release_recheck_2026-03-30_181927.md
阶段验证与总控流水可复跑且通过 PASS superpowers_stage_validation_2026-03-30_181925.md + superpowers_release_pipeline_2026-03-30_181925.md

4. 限制与说明

  1. PHASE-07 仍为 DEFERRED说明真实 staging 参数尚未完成闭环。
  2. 当前结论仍应保持 CONDITIONAL_GO/NO_GO,不得提前判定生产 GO
  3. 本次更新重点是“口径对齐与防误判”,不替代真实联调结果。

5. 下一步

  1. 使用模板执行真实 staging 回填,补齐 M-013~M-016 与 M-021 的生产口径证据。
  2. 回填完成后重跑 superpowers_release_pipeline.sh 并更新签署版 final_decision
  3. 若 PHASE-07 转为 PASS再触发下一轮专家复审。